# Phase 5 — Stand-up & Build

`Apr – May 2027 →`

{% hint style="info" %}
**Objective:** Stand up the lead hub (commission all 7 zones), begin producing, instrument everything, cascade the learnings, and start the equity flywheel.
{% endhint %}

## Workstreams

* **5.1 Zone commissioning** — build out + equip Yard, Depot, Workshop, Forge, Station, Hall, Loft; safety certifications; first material intake → first fabrication.
* **5.2 Workforce live** — member-builder crews + trainees through the Hall → Workshop → site pipeline; contractors for specialized buildout.
* **5.3 Sweat-equity & EQTBLT live** — contribution logging → token equity accrual (on the platform); quadratic governance active at the local node; member ownership begins its climb toward majority.
* **5.4 First output** — pipeline-B sites enter deconstruction/construction using hub-recovered materials; first homes and commercial space.
* **5.5 Instrumentation** — actuals vs. pro forma (cost + schedule variance); SOPs packaged for cohort inheritance.

## Inputs → Outputs

| Inputs                  | Outputs / artifacts                                                                                                   |
| ----------------------- | --------------------------------------------------------------------------------------------------------------------- |
| Stand-up-ready packages | Lead hub operating (zones live) · first material/fabrication throughput · **Build Playbook v1** · live EQTBLT accrual |

## Exit gate · KPIs · risks

* **Exit gate / Year-One close:** lead hub(s) operating and producing; cohorts behind on the same track; the flywheel turning.
* **KPIs:** zones commissioned · material throughput · contributors active · sweat-equity hours logged · EQTBLT issued · first housing starts · **the three-metric proof scorecard.**
* **Risks:** buildout cost overruns · equipment lead times · labor availability · QC across parallel sites · zone-specific safety/compliance.

{% hint style="success" %}
This is where the proof gate is cleared — the cost-reduction scorecard on a first real build, on a real address. **Round 1 ends here, proven.**
{% endhint %}

{% content-ref url="/pages/5sCspFNudRIP48xu4uBG" %}
[The Build Process](/execution/build-process.md)
{% endcontent-ref %}

{% content-ref url="/pages/cxpedDRSDv2tK0qNPFDf" %}
[The Proof Gate](/invest/proof-gate.md)
{% endcontent-ref %}


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation dynamically by asking a question.

Perform an HTTP GET request on the current page URL with the `ask` query parameter:

```
GET https://blueprint.builtbydao.com/execution/phase-5-standup-build.md?ask=<question>
```

The question should be specific, self-contained, and written in natural language.
The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.